Expansion of Maryland Toll Lane Project Increases Cost Five-Fold to $1.1 Billion

A $210 million project to add a single, 7-mile express toll lane on Interstate 95 north of Baltimore was just expanded to two lanes for 10 miles. Financing will rely on toll revenue. Unlike HOT lanes, every motorist will pay to use the lanes.

2 minute read

June 19, 2018, 11:00 AM PDT

By Irvin Dawid


Toll Lane Project

Maryland Transportation Authority / I-95 ETL Northbound Extension

"A plan to extend express toll lanes (ETLs) on Interstate 95 north of Baltimore into Harford County [see map (pdf)] will be greatly expanded from what was originally proposed, it was announced [pdf] Friday morning by the Maryland Transportation Authority [MDTA], which operates the highway," reports Allan Vought of The Aegis on June 15.

The [I-95 ETL Northbound Extension] will add two northbound toll lanes in the center of the highway from ... where existing express lanes end to ... Abingdon, a distance of about 10 miles, according to MDTA. 

The project is somewhat unusual in that the lane additions are only in the northbound direction, while no toll lanes exist in this southbound stretch, according to an email from Vought. Unlike other express lane projects in Maryland, such as the $7.8 billion express toll lane additions proposed for Interstate 270 and the Capital Beltway, as well as in neighboring Virginia, financing will be done by the state rather than a public-private partnership. 

MDTA said Gov. Laryy Hogan’s administration will commit an additional $890 million to the project, originally budgeted at $210 million, bringing the total to $1.1 billion. The state will recoup the cost of building the new toll lanes and related construction through toll collections, MDTA spokesperson John Sales said.

Unlike the more common high occupancy toll (HOT) lanes that exist in Virginia and other states, there are no exemptions from paying the toll for carpools or clean special fuel vehicles. As posted June 12, about two-thirds of the vehicles on the 66 Express Lanes Inside the Beltway in Northern Virginia from 8:15 a.m to 8:30 a.m. "are riding free — motorcycles, buses, and cars carrying at least two people with an E-ZPass Flex switched to HOV mode." These lanes no longer exempt so-called hybrid vehicles. 

According to MDTA, the state doesn't use HOT lanes "because of limitations on the ability to enforce lane restrictions and occupancy requirements."

Max Smith of WTOP News reports that enforcement was more of a problem for the 66 Express Lanes when it was restricted to high occupancy vehicle use only, with a 50 percent violation rate. After the conversion to HOT lanes in December, the violation rate plummeted, though some solo drivers are illegally using an E-ZPass Flex switched to HOV mode to get a free ride.

Adding the two lanes to I-95 will require the reconstruction of at least four bridges to accommodate the widened interstate and reconstruction of two interchanges.

The project is expected to get underway in early 2019 with an estimated completion sometime in 2026, according to Sales.

Hat tip to IBTTA Smart Brief.

Friday, June 15, 2018 in The Baltimore Sun

Young Professional

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban and Environmental Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban and Environmental Planner

Get top-rated, practical training for planners

"Planetizen federal action tracker" logo superimposed over black and white image of US Capitol dome.

Planetizen Federal Action Tracker

A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

October 28, 2026 - Zachary Whalen

A car drives through a puddle, making a large splash. Rain pours down.

California plans to bury El Niño’s downpour

If the state plays its cards right, it may be able to store a billion acre-feet of El Niño’s water in aquifers.

October 28, 2026 - Grist

Lake Powell with much of the water evaporated.

Desperate measures: Advocates weigh draining Lake Powell to fill Colorado River

Draining the reservoir could reduce evaporation losses by a couple hundred thousand acre-feet.

October 30, 2026 - Yale Environment 360

A group of officials stand in a patch of dirt holding golden shovels and white hardhats.

California city breaks ground on transit connector

The project includes three mobility hubs and a pedestrian bridge.

4 hours ago - Mass Transit

People walking by a brick school in Cambridge.

After public outcry, Massachusetts city releases housing development tracker

Cambridge’s tracker currently shows 250 housing projects in various stages of development.

5 hours ago - Smart Cities Dive

A rendering of the park, with green grass and a bass sculpture that looks like several tall arches in a row.

40 years after approval, Chicago breaks ground on new park

The park honors Jean Baptiste Point du Sable, the city’s first permanent non-native settler.

6 hours ago - Block Club Chicago