WMATA's SafeTrack: Behind Schedule and Over Budget

The SafeTrack repair program has shut down Metrorail lines for much of 2016—and the price for the repairs to the system keep going up.

1 minute read

November 21, 2016, 2:00 PM PST

By James Brasuell @CasualBrasuell


Transit Fail

Elvert Barnes / Flickr

"Metro’s SafeTrack maintenance program will cost significantly more than anticipated and take at least three months longer to complete," reports Martine Powers, based on the information provided in a progress report released last week.

"The report by the Federal Transit Administration estimates that the total cost of the project will be $118.8 million — nearly twice the $60 million price tag Metro General Manager Paul J. Wiedefeld floated in June," adds Powers.

The article goes into detail about where the WMATA's cost estimates and the cost estimates of the Federal Transit Administration differ. Then there is this other detail that will disappoint, but probably not surprise, transit users in the Washington, D.C. region: the progress report estimates that the program will end in June, rather than the originally estimated March completion date.

Wednesday, November 16, 2016 in The Washington Post

Young Professional

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban and Environmental Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban and Environmental Planner

Get top-rated, practical training for planners

"Planetizen federal action tracker" logo superimposed over black and white image of US Capitol dome.

Planetizen Federal Action Tracker

A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

September 16, 2026 - Zachary Whalen

Passengers board an Amtrak train under a cloudy sky.

Amtrak, CN end decades-long dispute with eight-year agreement

The new operating agreement establishes an updated framework for the companies to work together, including processes to resolve disputes.

September 18, 2026 - Mass Transit

The Gross Reservoir, a large body of water surrounded by trees and mountains.

Judges permit Denver to divert 77,000 acre feet from the Colorado River for reservoir expansion

Overuse and climate change have caused the Colorado River’s water levels to plummet.

September 18, 2026 - Inside Climate News

A painted bus lane in NYC.

NYC DOT wants faster, more permanent street upgrades

The city is examining ways to build more concrete infrastructure without getting entangled in 'decades-long' projects.

September 21 - NYC Streetsblog

A woman looks at a utility bill.

'Something we’ve never seen before:' rising utility rates could strain city finances nationwide

Data centers, climate change and other factors have caused utility rates in the United States to increase by 38% since 2020.

September 21 - Smart Cities Dive

A person scuba diving in a coral reef off Guam.

Trump to overrule local leaders, lease millions of acres of America’s Pacific Island territories’ seafloors to mining companies

International law says that the Indigenous people of America’s territories have a right to prior and informed consent regarding projects that impact their countries.

September 21 - Grist