Sound Transit had to deliver bad news last week about cost overruns in the design and engineering phase of the East Link rail project that will cross Lake Washington along the path of Interstate 90.
"Before the first tracks [of the East Link] are installed, Sound Transit must spend as much as $20 million in unexpected engineering costs to finish designing the world’s only rail corridor over a floating bridge, as it extends service to the Eastside," reports Mike Lindblom.
Ron Lewis, project director for East Link, "shared the blame between his own team and engineering giant Parsons Brinckerhoff (PB)," according to Lindblom, for "inefficiencies" in the workflow that led to the cost overrun. Parson Brinkerhoff, however, "could now earn $56 million instead of its earlier $36 million contract figure, which began at $28 million in 2012."
So while these design snafus are being ironed out, several major milestones still await the project before construction can begin. Lindblom report, for instance, that "Sound Transit’s final I-90 design, to be approved by the Washington State Department of Transportation (WSDOT), is expected to stretch another year, until late 2016."
The East Link is expected to open in 2023, connecting the International District/Chinatown Station, Bellevue, and Overlake. The funding for the $3.7 billion East Link line was made possible when voters approved a sales-tax increase on a 2008 regional ballot measure.
Read the full story: Extra $20 million OK’d to finish East Link light-rail design
Planetizen Federal Action Tracker
A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.
‘Going backwards:’ Baltimore mayor, students rally against state's transit funding plan
Maryland's proposed six-year plan provides no funding for Baltimore’s BMORE bus program and reduces its road maintenance funding.
Detroit to transform waterfront with $2.2 billion investment
Developers will convert about 18 acres of unused parking lot space into civic spaces.
Newsom vetoes high-speed rail supervision bill after agency receives condemnatory audit
The audit found the CHSRA approved almost $600,000 in unallowable travel expenses.
Nation sees first electric plane-boat hybrid take off in public demo
The Viceroy Seaglider can fly at speeds of 180mph for up to 180 miles.
One of nation’s poorest counties to receive $6 billion data center
The developers estimate the project will create 200 permanent jobs and 1,000 temporary construction jobs.
FREE Course: Walkable City 1: Why Walkability?
After describing his path towards focusing on walkability as the essence of good planning, Jeff Speck marches through his five principal reasons for making more walkable places.
Reinventing Malls: Planning Alchemy—Turning Gray Fields Into Gold
The course focuses on the opportunities and imperatives that shape reinvention of mall sites.
City of Thousand Oaks
City of Wisconsin Rapids
Harvard University Graduate School of Design
The Architects Foundation
University of Cincinnati Online
Northern Illinois Transit Authority (NITA)
The Pocatello Development Authority
The Urban Renewal Agency of the City of Pocatello