The $2.2 billion Salesforce Transit Center, which opened to much celebration on Aug. 11, closed down abruptly Sept. 25 after workers found a cracked steel beam. A second cracked beam was later found. Work began Sunday to shore up the structure.

"The cracked beam was spotted Tuesday morning by workers installing ceiling panels on the center’s third-floor bus platform, and concern over its potential failure prompted city officials to close the terminal and some streets at 4:30 p.m," report for the Chronicle on Sept. 28.
They shunted rush-hour commuters to the nearby Temporary Transbay Terminal, which had been used during the center’s construction.
During an overnight inspection of the center, which opened on Aug. 11, a second crack was discovered, though smaller than "[t]he initial tear [that] runs about 2½ feet long and 4 inches deep through the bottom of a 60-foot-long beam that supports both the center’s celebrated rooftop park above and a bus deck below," reported the Chronicle's and
Representatives of the Transbay Joint Powers Authority, which built and operates the transit center, said Wednesday they didn’t know the causes of the cracks, but they remained concerned about the potential for the beams to fail. Fremont Street, which passes under the center, also is scheduled to stay closed through Oct. 5.
The Chronicle's urban design critic, John King, delves into the structural engineering aspects of the three-block, 1,500-foot building that "twice span major roadways."
Those spans are supported by just four massive beams. Two of them have cracked.
What makes the situation so worrisome is that the cracked girders are the primary means of support for the transit center as it spans Fremont. The only things below the bus deck are sidewalks and asphalt.
King interviewed many structural engineers for the story.
“You’ve got a bus deck hanging from a column that in turn is held up by two cracked beams,” said Joe Maffei, founder of San Francisco’s Maffei Structural Engineering...“I think we are lucky that there was not a collapse.”
While it is not known what caused the cracking of the steel beams which were fabricated by Herrick Corp. in Stockton, Calif., King offers one possiblity:
The most troubling scenario is that the design by Thornton Tomassetti structural engineers and Pelli Clark Pelli Architects didn’t adequately account for the twin pressures of a bus deck and rooftop.
"Hydraulic jacks and newly fabricated steel beams arrived Sunday morning ... where they’ll be used to shore up the spot over Fremont Street where cracks were discovered," reports Michael Cabanatuan on Sept. 30.
By midnight Sunday, Mark Zabaneh, director for the Transbay Joint Powers Authority, said the first of three phases of shoring up the transit center should be completed. It’s not yet clear how long the whole process will take, but by Monday or Tuesday, he said, authorities should have a better idea of when they can partially open Fremont Street.
Once crews install the temporary bracing, it will relieve weight from the damaged girders and allow extensive testing to help determine the cause of the cracking. It could take a week or longer to get results of those tests, he said.
Matier and Ross note the proximity of the transit center to two other engineering failures:
- The center sits next to the troubled Millennium Tower, which has sunk 18 inches since it opened in 2009.
- The cracked beam is also reminiscent of the cracked bolts that plagued the eastern span of the Bay Bridge.
Related in Planetizen
-
San Francisco's Transbay Transit Center Opens This Weekend, August 8, 2018
FULL STORY: It looks simple, but it’s not. Complexity of Transbay Transit Center raises risks

Rethinking Redlining
For decades we have blamed 100-year-old maps for the patterns of spatial racial inequity that persist in American cities today. An esteemed researcher says: we’ve got it all wrong.

Planetizen Federal Action Tracker
A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

California High-Speed Rail's Plan to Right Itself
The railroad's new CEO thinks he can get the project back on track. The stars will need to align this summer.

US Senate Reverses California EV Mandate
The state planned to phase out the sale of gas-powered cars by 2035, a goal some carmakers deemed impossible to meet.

Trump Cuts Decimate Mapping Agency
The National Geodetic Survey maintains and updates critical spatial reference systems used extensively in both the public and private sectors.

Washington Passes First US ‘Shared Streets’ Law
Cities will be allowed to lower speed limits to 10 miles per hour and prioritize pedestrians on certain streets.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
City of Camden Redevelopment Agency
City of Astoria
Transportation Research & Education Center (TREC) at Portland State University
Regional Transportation Commission of Southern Nevada
Toledo-Lucas County Plan Commissions