The historic precipitation that fell on the state of California in past months poses a unique and unanticipated threat to the state’s big infrastructure project in the Central Valley.
“Recent rainstorms that have created flooding in some parts of Kings and Tulare counties have also ground work to a halt at several key construction sites for California’s high-speed rail project,” Tim Sheehan for the Fresno Bee. While several work sites are shut down due to the current flooding, officials expect the problem to continue into the summer, as a historic snow pack melts and sends even more water down the state’s various waterways.
Work is continuing along other stretches of the 119-mile stretch of the rail line currently under construction, but on sections impacted by flooding, construction crews have been working to help protect communicates from flooding, according to the article.
Meanwhile, high-speed rail officials report that the project is proving as resilient as it was designed. “The rail line has been designed to cope major floods; viaducts and a railbed that will elevated above the level of the surrounding land are expected to minimize the risk of damage from future floods,” according to the source cited in the article below.
“But it’s the seasonal flow of irrigation ditches and canals that the rail line must cross that represent uncertainty in how fast work can progress this coming fall and winter,” according to Sheehan.
The California High-Speed Rail project has faced numerous challenges through the years, from shifting political winds to cost overruns and planning challenges.
FULL STORY: California’s beleaguered bullet train faces another hurdle: flooding from melting snow
Planetizen Federal Action Tracker
A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.
The state-sanctioned urbicide of Austin
People don’t kill cities. Freeways do.
US to reduce Colorado River water deliveries to Mexico
A new Colorado Treaty amendment reduces Mexico’s Colorado River water allocation by 250,000 acre feet.
5 New England states march closer to 800 megawatt wind energy project
Securing federal approval for the project may be complicated under the Trump administration, which has historically been hostile towards domestic wind power.
Baltimore to break ground on $50 million Transit Priority Project
The project will bring faster bus trips, safer streets and better bike connections to Baltimore.
Airbnb launches $250 million 'last-dollar financing' housing accelerator, makes first investment in Austin
The company will put $6.4 million towards affordable housing development in Texas’ capital.
FREE Course: Walkable City 1: Why Walkability?
After describing his path towards focusing on walkability as the essence of good planning, Jeff Speck marches through his five principal reasons for making more walkable places.
Reinventing Malls: Planning Alchemy—Turning Gray Fields Into Gold
The course focuses on the opportunities and imperatives that shape reinvention of mall sites.
Eagle County Government
Harvard University Graduate School of Design
Nashville Planning Department
The Architects Foundation
University of Cincinnati Online
The Pocatello Development Authority
The Urban Renewal Agency of the City of Pocatello
Journal of the American Planning Association