State Documents Reveal Woes at Pioneering Atlantic Yards Modular Tower

What was promised as the tallest building in the world built by modular construction is delayed and the subject of lawsuits. State documents, recently made public, describe water damage, tolerance challenges, and unanticipated repairs.

2 minute read

September 2, 2015, 6:00 AM PDT

By NormanOder


The Atlantic Yards apartment tower known as B2 officially launched in December 2012 with great fanfare and high hopes, and not just because of what developer Forest City Ratner proposed to build: 32 stories housing 363 apartments, half of them affordable. It was that B2, nearly flush to the Barclays Center, would be the world's tallest modular tower, with its flooring, fixtures, appliances, and facades delivered within a metal-framed chassis some 10' high, 15' wide, and 30' long. Forest City said it had "cracked a code" and claimed an "iPhone moment".

Two additional Atlantic Yards towers would start within the next 12 to 18 months, among the 6,430 apartments—2,250 of them below-market—planned for the project, all to be built modular. B2's 930 mods—which Forest City CEO MaryAnne Gilmartin likened to "shrink-wrapped apartments—would be made at a new factory at the Brooklyn Navy Yard. The first mods arrived at Dean Street and Flatbush Avenue in December 2013 with a proud "Made in Brooklyn" wrapping.

B2's pioneering approach was seen as more than just an intriguing development at the highly contested Atlantic Yards site. Its designers and admirers thought the modular method might lower the cost of affordable housing, creating a new model for high-rise, union built apartments.

Today, the reality of B2 has not matched the anticipation. The building—delayed, stalled, and since re-started to reach half its ultimate height—will take more than twice as long as promised and cost far more than projected. B2, also known as 461 Dean Street, remains mired in lawsuits filed by Forest City and its former partner Skanska, with dueling charges of incompetent execution and flawed design.

While Forest City Chairman Bruce Ratner in July 2014 claimed on NY 1 that modular "worked out technically perfectly," with delays the only problem, state documents acquired via a Freedom of Information Law (FOIL) request paint a more ominous picture. Half of the first 39 apartments suffered significant water damage. The first four floors were "largely gutted," according to reports from consultant STV, which serves as owner's representative for Empire State Development (ESD), the state agency overseeing/shepherding the entire Atlantic Yards project, which has been renamed Pacific Park Brooklyn.

The builders got so skittish that, on the 9th and 10th floors, drywall sections of the ceilings and walls closest to the windows were omitted from mods, to be installed later, undermining the concept of completing as much as possible in the factory.

Tuesday, September 1, 2015 in City Limits

portrait of professional woman

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban Planner

Use Code 25for25 at checkout for 25% off an annual plan!

Logo for Planetizen Federal Action Tracker with black and white image of U.S. Capitol with water ripple overlay.

Planetizen Federal Action Tracker

A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

May 7, 2025 - Diana Ionescu

Person in yellow safety suit and white helmet kneels to examine water samples outdoors on a lake shore.

USGS Water Science Centers Targeted for Closure

If their work is suspended, states could lose a valuable resource for monitoring, understanding, and managing water resources.

May 1, 2025 - Inside Climate News

Wide suburban road with landscaped median and light pole banners advertising local amphitheater.

End Human Sacrifices to the Demanding Gods of Automobile Dependency and Sprawl

The U.S. has much higher traffic fatality rates than peer countries due to automobile dependency and sprawl. Better planning can reduce these human sacrifices.

April 29, 2025 - Todd Litman

Wasco Viaduct under construction in California's Central Valley as part of California High-Speed Rail project.

Trump: Federal Government Won’t Pay for California HSR

The President has targeted federal funding for the California bullet train project since his first administration.

May 8 - The Fresno Bee

Bird's eye view of Salesforce Park in San Francisco, CA.

San Francisco Enhances Urban Planning Initiatives with Green Infrastructure

San Francisco incorporates green infrastructure in its city development initiatives, elevating the importance of sustainability in urban planning.

May 8 - The Daily Californian

Aerial view of Chicago with river in foreground.

Chicago Approves Green Affordable Housing Plan

The Mayor’s plan calls for creating a nonprofit housing corporation tasked with building affordable housing that meets Green Building standards.

May 8 - CBS News Chicago

Urban Design for Planners 1: Software Tools

This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.

Planning for Universal Design

Learn the tools for implementing Universal Design in planning regulations.

Comprehensive Bikeway Design Workshop

Transportation Research & Education Center (TREC) at Portland State University

Early Bird Deadline – save on your tuition fee!🚨

Institute for Housing and Urban Development Studies (IHS)