Seattle's First Hill Streetcar Delayed by Late Arrival of Trains

It's not a mishap on the scale of the Bertha tunnel-boring machine stuck under Seattle's Downtown waterfront, but contractors underestimated the amount of time necessary to build seven trains for the city's new streetcar line.

1 minute read

September 28, 2014, 9:00 AM PDT

By James Brasuell @CasualBrasuell


"The rails are set on Broadway. The electric wires have been strung overhead. A green bike lane was finished last year, followed by the concrete boarding platforms," reports Mike Lindbloom. Yet, "[passenger] service on the $134 million project has been delayed until “as early as the first quarter of 2015." The news of the delay came in a memo to the Seattle City Council.

"Train-builder Inekon, based in the Czech Republic, underestimated how long it would take to design and build the seven trains, said Ethan Melone, streetcar program manager for the Seattle Department of Transportation." The delay, however, will come at a price for Inekon, which will pay penalties of $25,000 the first day and $1,000 for each additional day of delay.

Barring any additional setbacks, this final delay means the project will arrive a year-and-a-half later than the city's original goal.

Tuesday, September 23, 2014 in The Seattle Times

portrait of professional woman

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban Planner

Use Code 25for25 at checkout for 25% off an annual plan!

Redlining map of Oakland and Berkeley.

Rethinking Redlining

For decades we have blamed 100-year-old maps for the patterns of spatial racial inequity that persist in American cities today. An esteemed researcher says: we’ve got it all wrong.

May 15, 2025 - Alan Mallach

Logo for Planetizen Federal Action Tracker with black and white image of U.S. Capitol with water ripple overlay.

Planetizen Federal Action Tracker

A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

May 14, 2025 - Diana Ionescu

Front of Walmart store with sign.

Walmart Announces Nationwide EV Charging Network

The company plans to install electric car chargers at most of its stores by 2030.

May 7, 2025 - Inc.

Regeneration of contaminated industrial land used for waste dumping, West Midlands, UK, 2006 .

EPA Awards $267 Million to Clean Up and Reuse Contaminated Sites

The EPA is investing the funds to clean up and redevelop contaminated sites nationwide, supporting economic growth, community revitalization, and environmental restoration.

May 18 - Environmental Protection

Archway made of bikes in Knoxville, Tennessee over Tennessee River.

Knoxville Dedicates $1M to New Greenway

The proposed greenway would run along North Broadway and connect to 125 miles of existing trails.

May 18 - WATE

25mph speed limit sign with digital "Your Speed" sign below it.

Philadelphia Launches ‘Speed Slots’ Traffic Calming Pilot

The project focuses on a 1.4-mile stretch of Lincoln Drive where cars frequently drive above the posted speed limit.

May 18 - WHYY