New York City Transportation Commissioner Polly Trottenberg compared the project to replace a section of the Brooklyn-Queens Expressway in Brooklyn heights as New York's "Big Dig."

"On Thursday afternoon, the New York City Department of Transportation presented two plans for replacing the crumbling, 1.5-mile section of the Brooklyn-Queens Expressway that passes through Brooklyn Heights and DUMBO and supports the beloved Brooklyn Promenade," reports Dana Rubinstein.
"Option one, the 'innovative' choice that city officials clearly prefer, would take six years (instead of eight-plus) and result in less appalling traffic nightmares. During construction, however, officials would build a six-lane highway adjacent to the Brooklyn Promenade," according to Rubinstein.
According to Rubinstein, "option two, the 'traditional approach,' will cost more, take longer, result in fewer long-term community benefits and require the permanent erection of a roadway directly above Furman Street. It is also likely to result in significantly more traffic, with many more trucks spilling over onto local streets."
Rubinstein provides more details on the construction measures each option entails, and notes an increasing price tag for the project—from an initial estimate of $1.7 billion in 2016, to today's $3 billion.
The day after the announcement of the proposed alternatives, the story took a somewhat surprising turn. MTA Chairman Joe Lhota, whose agency is faced with a protracted shut down of a key subway link between Brooklyn and Manhattan in addition to numerous other infrastructure and service challenges, took to Twitter to voice displeasure with the possibility that the BQE might be shut down for six years. Here's the tweet Lhota has since deleted:
— Amy Spitalnick (@amyspitalnick) September 21, 2018
Dana Rubinstein wrote another article examining Lhota's statement. The lede is as snarky as it gets: "MTA Chairman Joe Lhota, whose subway system continues to founder, has finally encountered a piece of news terrible enough to turn him into an activist."
FULL STORY: De Blasio administration outlines 'Big Dig' scenario for Brooklyn Heights

Planetizen Federal Action Tracker
A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

San Francisco's School District Spent $105M To Build Affordable Housing for Teachers — And That's Just the Beginning
SFUSD joins a growing list of school districts using their land holdings to address housing affordability challenges faced by their own employees.

The Tiny, Adorable $7,000 Car Turning Japan Onto EVs
The single seat Mibot charges from a regular plug as quickly as an iPad, and is about half the price of an average EV.

With Protected Lanes, 460% More People Commute by Bike
For those needing more ammo, more data proving what we already knew is here.

In More Metros Than You’d Think, Suburbs are Now More Expensive Than the City
If you're moving to the burbs to save on square footage, data shows you should think again.

The States Losing Rural Delivery Rooms at an Alarming Pace
In some states, as few as 9% of rural hospitals still deliver babies. As a result, rising pre-term births, no adequate pre-term care and "harrowing" close calls are a growing reality.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
Smith Gee Studio
City of Charlotte
City of Camden Redevelopment Agency
City of Astoria
Transportation Research & Education Center (TREC) at Portland State University
US High Speed Rail Association
City of Camden Redevelopment Agency
Municipality of Princeton (NJ)