California High-Speed Rail: Under Construction for Two Years Despite Obstacles

In spite of a host of problems, over 1,000 parcels have been acquired and construction is occurring in nine areas in the Central Valley, centering on Fresno. Limited service from San Francisco to Bakersfield could begin in 2025.

3 minute read

February 17, 2017, 2:00 PM PST

By Irvin Dawid


"America’s biggest infrastructure project is both in limbo and full-speed ahead," reports Kurtis Alexander for the San Francisco Chronicle. It's become the poster child of boondoggles for Republicans in Sacramento and the nation's capital, but in the Central Valley, particularly around its largest city, Fresno, it's presence can not be overlooked, literally-speaking in some areas.

Far from the wrangling in Sacramento and Washington, work on the first 119-mile segment, from Madera to just outside Bakersfield, has been under way for almost two years.

Just south of downtown Fresno, the largest undertaking so far — a half-mile-long viaduct that will lift trains from the city into distant farmland — is taking shape in an area of old factories and warehouses. Already, the new structure is a monolith helping define the Fresno skyline....The columns of the superstructure stand nearly 80 feet tall, while the bridge deck is emerging as a sleek, aerial concourse.

It’s very satisfying to see,” said California High-Speed Rail’s Central Valley director, Diana Gomez, as she led a tour of the loud, muddy construction site. “Everyone can see this piece from Highway 99.”

Alexander writes that the project is not being done in one, expanding location, as one might expect, but at nine major sites. Twelve miles north of the Fresno viaduct described above, "a nearly mile-long viaduct is rising over the San Joaquin River, while about 25 miles to the north, in Madera County, a bridge is materializing across the Fresno River."

One of the most significant activities, moving six lanes of Highway 99 about 100 feet to the west for 2 miles, will allow trains to squeeze through a dense part of central Fresno.

“There’s really no place yet you can stand and see for miles and miles and say, ‘Yeah, it’s coming together,’” said Dan Richard, chair of the Rail Authority's governing board, looking up at the emerging bridge over the San Joaquin River. “But once these few projects get done, connecting them comes fast.”

However, litigation by opponents living in the Central Valley, "planning snafus and problems with land acquisitions have set the project back at least three years."

It's uncertain whether the first, 500-mile phase from San Francisco to San Jose, will receive sufficient funding to be built. The California High-Speed Rail Authority was expecting to receive more federal funding, which Congress has since eliminated, and although some private rail operators have shown some interest, none are willing to invest in the project, unlike the nation's other high-speed rail project connecting Dallas to Houston.

"Texas Central Partners plans to begin construction on the rail in late 2017 and will work closely with Japan Railway to localize the firm’s Shinkansen bullet train technology," reported Bill Hethcock for the Dallas Business Journal last May. "The project is scheduled for completion in 2021 with the first full year of operations in 2022."

The California High-Speed Rail Authority hopes to launch bullet trains from San Francisco to Bakersfield by 2025, but without new funding, running tracks to Los Angeles will be challenging.

Sunday, February 12, 2017 in San Francisco Chronicle

portrait of professional woman

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban Planner

Get top-rated, practical training

Close-up of "Apartment for rent" sign in red text on black background in front of blurred building

Trump Administration Could Effectively End Housing Voucher Program

Federal officials are eyeing major cuts to the Section 8 program that helps millions of low-income households pay rent.

April 21, 2025 - Housing Wire

Logo for Planetizen Federal Action Tracker with black and white image of U.S. Capitol with water ripple overlay.

Planetizen Federal Action Tracker

A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

April 30, 2025 - Diana Ionescu

Ken Jennings stands in front of Snohomish County Community Transit bus.

Ken Jennings Launches Transit Web Series

The Jeopardy champ wants you to ride public transit.

April 20, 2025 - Streetsblog USA

Close-up of white panel at top of school bus with "100% electric" black text.

Driving Equity and Clean Air: California Invests in Greener School Transportation

California has awarded $500 million to fund 1,000 zero-emission school buses and chargers for educational agencies as part of its effort to reduce pollution, improve student health, and accelerate the transition to clean transportation.

6 hours ago - California Air Resources Board

Aerial view of Freeway Park cap park over I-5 interstate freeway in Seattle, Washington at night.

Congress Moves to End Reconnecting Communities and Related Grants

The House Transportation and Infrastructure Committee moved to rescind funding for the Neighborhood Equity and Access program, which funds highway removals, freeway caps, transit projects, pedestrian infrastructure, and more.

7 hours ago - Streetsblog USA

"No Thru Traffic - Open Streets Restaurants" sign in New York City during Covid-19 pandemic.

From Throughway to Public Space: Taking Back the American Street

How the Covid-19 pandemic taught us new ways to reclaim city streets from cars.

April 30 - Next City