The Washington Nationals, winners of the 2019 World Series, almost needed to find a new home for the final games of the 2022 baseball season after Events D.C. failed to meet the terms of the certificate of occupancy for Nationals Park.

The D.C. Department of Consumer and Regulatory Affairs (DCRA) gave quite a scare to baseball fans in the nation’s capital, waiting until the 11th hour to extend a permit to play games in National Park, home of the Washington Nationals. Without the extension, the Nationals would have needed to find another place to play for the final two homegames of the season.
The permit in question was the D.C.-issued certificate of occupancy for Nationals Park, issued by the Department of Consumer and Regulatory Affairs in 2006, but ending on September 30, 2022—with two days left on the current season.
According to an article by Tristan Navera for the Washington Business Journal, the “2006 agreement with the D.C. Zoning Commission that set the nearly $700 million project into motion required that Events D.C., the stadium's owner, build out 46,000 square feet of of [sic] retail, services, entertainment or arts uses on the stadium premises.”
A few days after Navera reported the news of the potential demise of the baseball season in D.C., the DCRA granted a 15-month extension on the permit. Events D.C. ow has until December 31, 2023 to file plans to complete the required development on the southeast corner of the stadium site.
“Events D.C. has asked to downsize the development needed in the agreement so it can instead finish 17,000 square feet of retail partially built out along First Street SE. In filings with the D.C. Zoning Commission, which must sign off on the agreement, Events D.C. said the slowing of the real estate market during Covid-19 has made a lot of retail on this site impractical,” reports Navera in a more recent article, published after the extension.
“Giving Events D.C. a 15-month extension will give the Zoning Commission time to make its ruling and also to submit construction plans for review and approval,” according to a source cited in the article.
FULL STORY: D.C. agency will extend Nats Park's occupancy permit as owner works through development plans

Planetizen Federal Action Tracker
A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

Canada vs. Kamala: Whose Liberal Housing Platform Comes Out on Top?
As Canada votes for a new Prime Minister, what can America learn from the leading liberal candidate of its neighbor to the north?

The Five Most-Changed American Cities
A ranking of population change, home values, and jobs highlights the nation’s most dynamic and most stagnant regions.

San Diego Adopts First Mobility Master Plan
The plan provides a comprehensive framework for making San Diego’s transportation network more multimodal, accessible, and sustainable.

Housing, Supportive Service Providers Brace for Federal Cuts
Organizations that provide housing assistance are tightening their purse strings and making plans for maintaining operations if federal funding dries up.

Op-Ed: Why an Effective Passenger Rail Network Needs Government Involvement
An outdated rail network that privileges freight won’t be fixed by privatizing Amtrak.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
New York City School Construction Authority
Village of Glen Ellyn
Central Transportation Planning Staff/Boston Region MPO
Institute for Housing and Urban Development Studies (IHS)
City of Grandview
Harvard GSD Executive Education
Regional Transportation Commission of Southern Nevada
Toledo-Lucas County Plan Commissions