Plans for the 'Loop Trolley' in St. Louis Threatened by High Costs

Plans for the 2.2-mile Loop Trolley in St. Louis have encountered problems before—now planners and construction contractors reportedly have different ideas about how much it will take to build the line.

1 minute read

November 10, 2014, 9:00 AM PST

By James Brasuell @CasualBrasuell


"nextSTL has learned that bids to construct the long planned Loop Trolley have come in $11M above budget, threatening to permanently derail the project, according to Alex Ihnen. "The amount is more than 25% above the trolley’s $43M stated budget. Current plans call for the project to be re-bid without substantial reengineering."

Earlier in the project's planning history, a federal grant of $22 million was almost rescinded dude to lack of progress on the project. Now it looks like city officials are beginning to plan for the death of the project altogether. According to Ihnen, "nextSTL has learned that other partners are beginning to plan for the financial fallout if the project is never built. Efforts are underway to explore whether the $22M federal grant could be reassigned to another project within the St. Louis region. Meanwhile, supporters of the Loop Trolley are hoping additional federal funds will be made available."

Saturday, November 8, 2014 in nextSTL

"Planetizen federal action tracker" logo superimposed over black and white image of US Capitol dome.

Planetizen Federal Action Tracker

A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

November 11, 2026 - Zachary Whalen

A highway in Washington state.

Washington state to charge fee to drivers with fuel-efficient cars

Revenue from the fee will go towards supporting the state’s highways.

November 17, 2026 - The Urbanist

A rendering of the proposed computing campus and data center, an aerial shot of three rectangular, gray buildings and smaller square, white ones.

Illinois considers spending $1 billion in taxpayer money on data center

A quantum computing campus and data center are currently under construction in Chicago.

November 17, 2026 - Block Club Chicago

A data center near the water billows smoke into a clear blue sky.

Did data centers change how voters cast their ballots?

Texas, Ohio, and Georgia all flipped party control. But in rural counties, the effect of local data centers was mixed.

4 seconds ago - The Daily Yonder

An Airo transit driving behind a lake and in front of a dark forest.

Amtrak invests in eight new Airo trainsets

The new trainsets will begin serving passengers in 2031.

1 hour ago - Mass Transit

The HUD building in DC, a tall, gray building with many rows of small windows.

HUD to end aid for mixed-immigration-status households

The new rule is projected to impact 80,000 people, nearly half of whom are children.

2 hours ago - Smart Cities Dive

FREE Course: Walkable City 1: Why Walkability?

After describing his path towards focusing on walkability as the essence of good planning, Jeff Speck marches through his five principal reasons for making more walkable places.

Reinventing Malls: Planning Alchemy—Turning Gray Fields Into Gold

The course focuses on the opportunities and imperatives that shape reinvention of mall sites.