Amtrak Cascades Derailment Foreseen in Original Rail Plans

The cause of last month's deadly Amtrak crash south of Tacoma above Interstate 5 is attributed to the train traveling at 78 mph through a curve with a speed limit of 30 mph. The original plan for the bypass called for the elimination of that curve.

2 minute read

January 2, 2018, 1:00 PM PST

By Irvin Dawid


Much attention has been placed on the lack of an operational positive train control system which could potentially have prevented Amtrak Cascades #501 on its maiden voyage on Dec. 18 from speeding through a curve leading to a bridge over Interstate 5 where it derailed, with two cars falling onto the freeway below, killing three passengers and injuring over 100. Now attention is being placed on the curve itself.

On Dec. 22, Ted Mann of The Wall Street Journal reported that had the Washington State Department of Transportation (WSDOT) proceeded with their original plan for the bypass route, that curve would never have existed. Amanda Woods of the New York Post reports on Mann's piece (which is accessible only to WSJ subscribers).

"An $11 billion Washington State government plan to speed up passenger and freight rail service throughout the Pacific Northwest called for an elimination of the turn," reports Woods.

But that request was not included in the final design, once the state won federal funding for the [$180.7 million] Point Defiance railroad bypass south of Tacoma, Wash., The Wall Street Journal reported on [Dec. 22].

The plan was ditched because the turn in question was deemed too costly to remove, the outlet reported, citing documents and state officials.

The section where the train derailed “includes unsuitable sharp curvature,” according to schematic documents obtained by the paper.

Woods adds that while WSDOT has plans to improve the bypass route to increase speed, they do not include elimination of the deadly curve "because it wasn’t deemed necessary to support the number of round trips the state and Amtrak had planned for the corridor," a WSDOT spokeswoman told the the Journal.

According to WSDOT, trains will not use the bypass route or the new Tacoma station for the foreseeable future due to the Dec. 18 derailment.

Also on Dec. 22, the National Transportation Safety Board issued a press release based on "Initial Review of Amtrak Train Recorders."

About six seconds prior to the derailment, the engineer made a comment regarding an over speed condition.

Some experts have suggested the engineer was distracted, possible due to the presence of someone else in the cab. The term they use is "loss of situational awareness."

Friday, December 22, 2017 in New York Post

Young Professional

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban and Environmental Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban and Environmental Planner

Get top-rated, practical training for planners

"Planetizen federal action tracker" logo superimposed over black and white image of US Capitol dome.

Planetizen Federal Action Tracker

A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

October 28, 2026 - Zachary Whalen

A car drives through a puddle, making a large splash. Rain pours down.

California plans to bury El Niño’s downpour

If the state plays its cards right, it may be able to store a billion acre-feet of El Niño’s water in aquifers.

October 28, 2026 - Grist

A pencil rendering of Foundry Park, which shows skyscrapers and public green spaces.

Chicago breaks ground on $3 billion megadevelopment

The new neighborhood, titled Foundry Park, will one day host 3,700 residences.

October 23, 2026 - Chicago Sun Times

A rendering of a high speed rain station in California, with wide platforms and a sleep train with yellow highlights.

California High-Speed Rail Authority CEO resigns after $600,000 scandal

Under Ian Choudri, the authority used taxpayer dollars to fund first class flights and trips to nightclubs.

October 30 - Cal Matters

 A bridge stretches across the Missouri River at Chamberlain, South Dakota.

Want to study the Missouri River? Soon, you may need unanimous approval from 10 states

Legislation would require 10 governors’ permission to study or build projects moving water outside the basin.

October 30 - South Dakota Searchlight

Lake Powell with much of the water evaporated.

Desperate measures: Advocates weigh draining Lake Powell to fill Colorado River

Draining the reservoir could reduce evaporation losses by a couple hundred thousand acre-feet.

October 30 - Yale Environment 360