The high-profile Central Subway is in danger of running out of money, according to a federal watchdog.
"Muni’s $1.6 billion Central Subway project is nearly out of money," reports Joe Fitzgerald Rodriguez.
"An independent federal monitor warns in a new report that the San Francisco Municipal Transportation Agency may soon spend its last federal dollar for the project and exhaust the 'contingency' budget meant to cover cost overruns," adds Rodriguez.
The article traces the origins of the cost overruns to conflict between the SFMTA and the contractor Tutor Perini Corporation (Tutor). In recent months, Tutor officials have publically blasted outgoing SFMTA Director Ed Reiskin. Rodriguez also noted that "Tutor is known for aggressively pursuing cities with claims and change orders," and not just in San Francisco. "A July 14 report from the Wall Street Journal highlighted Tutor Perini’s $120 million lawsuit against the Port Authority of New York and New Jersey over 'delays and cost overruns' to construct the George Washington Bridge Bus Station in Manhattan," writes Rodriguez.
The project, once expected to be complete by 2018, is now scheduled for 2020. But if the budget runs out, and it's already "running on fumes," San Francisco could be left with a "train-less hole in the ground," according to Rodriguez.
FULL STORY: Central Subway contractor dispute threatens to bust budget
The state-sanctioned urbicide of Austin
People don’t kill cities. Freeways do.
US to reduce Colorado River water deliveries to Mexico
A new Colorado Treaty amendment reduces Mexico’s Colorado River water allocation by 250,000 acre feet.
New Jersey’s second-largest city bans standalone data centers
Jersey City will continue to allow co-location facilities, such as those meant for research institutions that store their own data.
Amtrak not solely to blame for New Jersey commuter rail's unreliability, report finds
A new study from the Garden State Initiative found that NJ Transit’s budget grew 20% across a 4 year period, but reliability declined significantly over the same period.
EPA erases limits on planet-warming pollution from power plants
Under Monday’s plan, power plants would still have some limits on how much mercury, arsenic and other contaminants they can emit.
Phoenix announces new on-demand transit service, more frequent RAPID buses
Both new services will launch in October, and are part of Phoenix's Project Effective Access Solutions for Easing Congestion.
FREE Course: Walkable City 1: Why Walkability?
After describing his path towards focusing on walkability as the essence of good planning, Jeff Speck marches through his five principal reasons for making more walkable places.
Reinventing Malls: Planning Alchemy—Turning Gray Fields Into Gold
The course focuses on the opportunities and imperatives that shape reinvention of mall sites.
Eagle County Government
Harvard University Graduate School of Design
Nashville Planning Department
The Architects Foundation
University of Cincinnati Online
The Pocatello Development Authority
The Urban Renewal Agency of the City of Pocatello
Journal of the American Planning Association