UC San Francisco is using a Campus Facilities Improvement Association (CFIA) to help build its Mission Bay campus. Infrastructure financing wonk Jim Chappell explains how it works.
Add FIAs, to CFDs, IFDs, and EIFDs, as public infrastructure project funding tools in the post redevelopment TIF California. FIA stands for Facilities Improvement Association, and CFD stands for Community Facilities District. IFD stands for Infrastructure Financing District, and EIFD stands for Enhanced Infrastructure Financing District. Jim Chappell, former director of the San Francisco Planning and Urban Research Association (SPUR) and development consultant explains how it's being used to build new facilities at UC San Francisco's Mission Bay campus. There, it's called the CFIA for Campus Facilities Improvement Association:
Traditionally, to build new buildings, UC has gone through a standard procurement process, developing a program, selecting an architect, overseeing the design, putting the building out to bid, and managing its construction. Public contract law requires competitive bidding, a good protection of the public’s dollars, but not always the best way to get the best building. In this traditional model, the State provides the money, the University owns and operates and maintains the building, again dependent on the legislature coming up with the annual draw.
Enter CFIA, a public private partnership that is a long-term deal (for 30 years minimum). It is a unique negotiated partnership that introduces risk and reward into the picture and arrives at a more flexible negotiated cost, and includes long-term management of the building by the private partner. CFIA is a not-for profit 501(c)(3) entity.
So far, we have successfully developed one building, and are just beginning the second. The Sandler Neurosciences Center is a 240,000 square foot $174 million LEED Silver laboratory building on the main quad, designed by Skidmore Owings and Merrill, and developed and maintained by a joint venture, Edgemoor McCarthy Cook.
Chappell goes on to explain how the CFIA works.
Read the full story: Show me the Money: Financing Public Facilities in the Age of Scarcity
Desperate measures: Advocates weigh draining Lake Powell to fill Colorado River
Draining the reservoir could reduce evaporation losses by a couple hundred thousand acre-feet.
Eastern Nebraska is running out of electricity
Data centers and electrification are straining eastern Nebraska’s grid, throttling economic development.
Move over, LA: St. Louis gears up for Olympics, invests millions in downtown redevelopment
The Missouri city will host the 2028 Olympic soccer group stage and knockout matches.
Mass. votes against statewide minimum lot size for single-family homes
Over 2 million residents voted on Question 7; it was decided by just over 30,000 votes.
Maryland’s $15 billion bridge project gains key approval
The Maryland Transit Authority said the project will create over 60,000 jobs and add $23 billion to the local economy.
‘No clear next steps’ for Chicago's permanent festival grounds
Eleventh Ward Ald. Nicole Lee has suggested Soldier Field as a possible location for the permanent event space.
FREE Course: Walkable City 1: Why Walkability?
After describing his path towards focusing on walkability as the essence of good planning, Jeff Speck marches through his five principal reasons for making more walkable places.
Reinventing Malls: Planning Alchemy—Turning Gray Fields Into Gold
The course focuses on the opportunities and imperatives that shape reinvention of mall sites.
City of Rosemead
Rutgers University, Edward J. Bloustein School of Planning and Public Policy
One Hundred Miles
University of Michigan School for Environment and Sustainability (SEAS)
Hunter College, City University of New York (CUNY)
The Architects Foundation
City of Cambridge
The Pocatello Development Authority
The Urban Renewal Agency of the City of Pocatello