When can a power company take your land for data center infrastructure?

Meeting data center power demands will mean building more transmission lines and acquiring more land to put them on.

4 minute read

July 21, 2026, 5:00 AM PDT

By Aaron Walayat

Many large power transmission towers loom over a small river with green trees on either side at sunset.

Power transmission lines. | ABCDstock / Shutterstock

The artificial intelligence boom in the United States is being matched by a data center building boom. There are more than 3,000 data centers in the U.S. and another 1,500 in development, according to a Pew Research Center analysis.

While President Donald Trump has promoted AI advancement, calling it crucial to economic and national security, polling shows that 7 in 10 Americans oppose the construction of AI data centers in their communities, citing higher utility bills, pollution, noise and the loss of green space. These centers, which hold computer servers that process words, images and lines of code for large language models such as ChatGPT, also use high amounts of water and electricity.

There is growing opposition to the infrastructure surrounding them, too, particularly the transmission lines needed to power them, which often must cross land belonging to private citizens.

Where private citizens refuse to sell their land, companies are turning to eminent domain, the government’s inherent power to seize private property without a landowner’s consent. But does a line built to serve a private data center qualify?

I’m a legal scholar who studies eminent domain issues, and I interpret today’s disputes over seizure of property for the benefit of AI infrastructure as the latest incarnation of a long-standing debate about the limits of taking private property for public use.

Why is expansion needed?

Data centers have massive power needs that can stress electrical grids and threaten their reliability. In 2024 they accounted for more than 4% of the nation’s total electricity use. Demand will grow as more are built. To meet this demand, power companies must build more transmission lines – and acquire land to put them on.

Across the U.S. – in states such as Georgia and Pennsylvania – power companies have looked to eminent domain to facilitate these goals.

What is eminent domain?

Power companies can approach landowners to purchase easements for transmission lines; if landowners refuse, the government might force a sale.

The government may take private land without consent if the seizure is for “public use” and if the landowner is given “just compensation,” according to the takings clause of the Fifth Amendment of the U.S. Constitution.

While the federal government has the power to initiate eminent domain actions – also called condemnations – most are done by state and local governments.

Governments can also delegate this power to private entities or “common carriers,” such as power and water companies, though every state has its own rules for whether and how these utilities can exercise eminent domain. In Texas, for example, the state Supreme Court has held that a project must “serve the public” and “cannot be built only for the builder’s exclusive use” in order to qualify as a common carrier.

What is the ‘public use’ standard?

While property may be taken only for “public use,” the U.S. Supreme Court has interpreted that requirement permissively. In its 2005 Kelo v. City of New London decision, the court held that economic development qualified, allowing New London, Connecticut, to seize homes for private development around a Pfizer facility. That redevelopment, however, never happened, and Pfizer eventually left New London.

In response to that decision – and the public backlash that followed – 45 states enacted eminent domain reform laws.

In addition to reform laws, some state supreme courts interpret the eminent domain provisions of their own state constitutions more restrictively. The supreme courts of Michigan, Ohio and Oklahoma have all prohibited seizing private property to give it to another private party purely for economic development.

This means private landowners may have more success challenging condemnation actions under their state constitutions than in federal court. Still, courts typically permit exercise of eminent domain by utilities such as power companies.

Workers in yellow and orange safety jackets walking next to power transmission lines and wind turbines in a field.
Workers at a power transmission station. Image: surachet khamsuk

What does this mean for data center expansion?

Suits challenging the seizure of property for transmission lines on the grounds of public use have mixed results.

For example, the supreme courts of South Dakota and Vermont have each affirmed seizures by power companies, determining that providing at least some energy and improved power grid reliability to in-state customers were valid public uses.

But this argument changes if transmission lines, some of which cross state lines, don’t benefit anyone in the state.

In 1984, for example, the Mississippi Supreme Court rejected a power company’s condemnation action because the transmission line in question would have run from Mississippi into Louisiana without benefiting any Mississippi customers.

These decisions suggest that as data centers increase energy demand and stress current infrastructure, seizing land to improve power grid reliability will likely qualify as public use, especially if the intention is to secure reliability for in-state customers.

Still, arguments around whether additional transmission lines actually serve in-state customers may give landowners grounds for a challenge.

—

Aaron Walayat is Assistant Professor of Law at the University of Dayton. 

This article is republished from The Conversation under a Creative Commons license. Read the original article.

"Planetizen federal action tracker" logo superimposed over black and white image of US Capitol dome.

Planetizen Federal Action Tracker

A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.

November 25, 2026 - Zachary Whalen

A highway in Washington state.

Washington state to charge fee to drivers with fuel-efficient cars

Revenue from the fee will go towards supporting the state’s highways.

November 17, 2026 - The Urbanist

A canyon wall filled with engravings of animals and people.

Trump to blast ‘hydrocarbon highway’ through ‘world’s longest art gallery’

Environmental and historic preservation groups are suing to stop the project.

November 22, 2026 - Grist

The MBTA's green line picking up passengers

MBTA Green Line project moved to next phrase of CIG program

The modernization effort will cost $4.08 billion.

November 27 - Mass Transit

A rendering of a family walking on the Atlanta Beltline

22-mile pedestrian and bike path to encircle Atlanta by 2030

The project will also support affordable housing.

November 27 - Smart Cities Dive

Smoke wafts up from the detonation site, in a field.

Army detonates nearly 5 tons of lead in Iowa

The detonation comes after days of delays and public outcry.

November 26 - CNN

FREE Course: Walkable City 1: Why Walkability?

After describing his path towards focusing on walkability as the essence of good planning, Jeff Speck marches through his five principal reasons for making more walkable places.

Reinventing Malls: Planning Alchemy—Turning Gray Fields Into Gold

The course focuses on the opportunities and imperatives that shape reinvention of mall sites.

Write for Planetizen