Portland Light Rail Extension To Open Early And Under Budget

The 5.8-mile Yellow Line running between the Rose Quarter and the Portland Expo Center will open May 1, ahead of schedule and about $30 million less than its $350 million budget. The original opening target was Sept. 7, 2004.
October 18, 2003, 1pm PDT | Abhijeet Chavan | @legalaidtech
Share Tweet LinkedIn Email Comments

The 5.8-mile Portland Interstate Max Light Rail line will open ahead of schedule and under budget. The new line has already attracted several business investments to the area, including a new grocery store.