The first comprehensive working paper on U.S. construction timelines also found that the permitting process for multi-family projects has slowed nationwide.
In Raleigh, North Carolina, an entire apartment building can be constructed in the same time it would take to approve a permit for that same building in San Francisco, according to a new economics working paper on housing construction timelines in the U.S. The paper is the first such comprehensive database of its kind in the nation.
The authors of the study — which still needs to undergo peer review and may be revised before publication — did not intend for the study to determine why some cities take so much longer to build new housing. However, they did find that longer permitting times are correlated with lower rates of housing production, and that permitting is slowing down nationwide. Marina Bolotnikova writes for Vox:
“We estimate that, in 2000, our standardized multi-family project had a 71-percent probability of approval within six months of applying for a permit,” the researchers write. “In 2025, that project had a 44-percent approval probability within six months.”
Delays in housing construction can cause homes to never be built at a time when the United States is “millions of homes in the hole,” and result in lost staff time that developers add to the cost of new homes, Vox reports.
Read the full story: How can we create more Indianapolises and fewer San Franciscos?
Planetizen Federal Action Tracker
A weekly monitor of how Trump’s orders and actions are impacting planners and planning in America.
Eastern Nebraska is running out of electricity
Data centers and electrification are straining eastern Nebraska’s grid, throttling economic development.
Study reveals best places in the U.S. for cycling, walking
New research from Streetlight Data examines bicycle and pedestrian miles per capita in the 100 largest U.S. cities by population.
Officials look to alter BART extension as price goes through the roof
Tariffs and the war with Iran are behind the rising cost.
To power data centers, Utah company may build hundreds of nuclear reactors on state land
In its permit application, Valar asked for the county to confirm that changes within its outlined plan would still be covered by the permit.
San Antonio is using environmental review to stall ICE detention center
San Antonio sued last month to pause work on the new detention center until the federal government studied its effect on the surrounding area.
FREE Course: Walkable City 1: Why Walkability?
After describing his path towards focusing on walkability as the essence of good planning, Jeff Speck marches through his five principal reasons for making more walkable places.
Reinventing Malls: Planning Alchemy—Turning Gray Fields Into Gold
The course focuses on the opportunities and imperatives that shape reinvention of mall sites.
City of Charlotte
City of Rosemead
Rutgers University, Edward J. Bloustein School of Planning and Public Policy
University of Michigan School for Environment and Sustainability (SEAS)
Hunter College, City University of New York (CUNY)
The Architects Foundation
City of Cambridge
The Pocatello Development Authority
The Urban Renewal Agency of the City of Pocatello