Seattle's Light Rail Halted

21 November 2000 - 2:00pm

After seven years and $25 million, progress on Seattle's 4.5-mile light rail tunnel have crashed to a halt.

"After seven years and more than $25 million worth of planning, progress on Seattle's 4.5-mile light-rail tunnel crashed to a halt yesterday when the Sound Transit board suspended negotiations with its tunnel-building firm.The whole tunnel project may lose its ticket to ride.Sound Transit's staff said even a new cost-cutting design was not enough to bring the Capitol Hill tunnel project within budget."

Source: The Seattle Post-Intelligencer, November 18, 2000
Bookmark and Share
Its very unsuitability for an urban center justifies its current usage as a suburban or ex-urban pattern.